Contract 74017 REL 41: 1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Project Number:
Title:
Lolo/Selway River Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
74017 REL 41
Contract Title:
1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
74017 REL 18: 1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
  • 84370: 1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
Contract History:

The Lolo Creek Watershed Restoration project (1996-077-02) has been an on-going project of the Nez Perce Tribe Fisheries Watershed Program and BPA since 1996. This unique and successful restoration partnership is implemented through agreements between the Nez Perce - Clearwater National Forests (NPCNFs), Nez Perce Tribe (NPT), and Bonneville Power Administration (BPA). The ultimate goal of the project is to restore the physical and biological characteristics of the watershed to provide quality habitat for anadromous and resident fish species that support the historical, cultural, and economic practices of the Nez Perce Tribe. In 2016, the Lolo Creek project was combined with the Selway River project, a newly funded BiOp effort initiated in 2011 to perform high priority watershed restoration actions in the Selway River watershed.

The Lolo Creek watershed contains proposed critical habitat for listed species Steelhead trout, potential critical habitat for Bull Trout, and has moderate habitat potential for Spring Chinook Salmon. Restoration in this watershed focuses on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing affects, fish passage barriers, and noxious weed infestations. Fish passage and habitat connectivity actions are prioritized primarily at road/stream crossings on both private and federal land, and native riparian revegetation and continuous riparian protection are also high priority actions.

The Selway River Watershed contains critical habitat for listed species Steelhead Trout, potential critical habitat for Bull Trout, and has moderate habitat potential for Spring Chinook Salmon. Restoration follows a ridge top to ridge top approach with implementation focused on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing effects, aquatic habitat connectivity, and exotic, invasive plant encroachment. The cost share for this project has been contributed by the Nez Perce - Clearwater National Forests who provides approximately 20% match including cash and in-kind contributions. Project planning and implementation responsibilities are also shared with the Nez Perce - Clearwater National Forests.



Completed contract work in the Lolo Watershed includes culvert prioritization and assessment, installation of an off-site water source, 29 culvert replacements, 11 culvert removals, 2600 ft. of stream bank stabilization, 14 large wood structures, 101.5 miles of road decommissioning, 23 miles of fence installation and maintenance, and over 24,000 native riparian trees and shrubs planted.

Completed contract work in the Selway Watershed includes culvert prioritization and assessment, installation of 10 culvert replacements, 41 miles road decommissioning surveys.
Account Type(s):
Expense
Contract Start Date:
02/01/2019
Contract End Date:
01/31/2020
Current Contract Value:
$615,965
Expenditures:
$615,965

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Anthony Broncheau Nez Perce Tribe No Interested Party anthonyb@nezperce.org (208) 843-7317
Marcie Carter Nez Perce Tribe Yes Supervisor marciec@nezperce.org (208) 621-3534
Anne Connor US Forest Service (USFS) Yes Interested Party aconnor@fs.fed.us (208) 476-8235
Arleen Henry Nez Perce Tribe No Interested Party arleenh@nezperce.org (208) 621-3833
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Jennifer Lord Bonneville Power Administration Yes COR jklord@bpa.gov (503) 230-5192
Ed Main Nez Perce Tribe No Interested Party edwardm@nezperce.org (208) 621-3539
Heidi McRoberts Nez Perce Tribe No Supervisor heidim@nezperce.org (208) 621-3548
Justin Peterson Nez Perce Tribe Yes Contract Manager justinp@nezperce.org (208) 621-3545
Tybee Sheidler Bonneville Power Administration No Interested Party tasheidler@bpa.gov (503) 230-3820
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Elham Zolmajd-Haghighi Bonneville Power Administration No Interested Party ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Documentation Submitted to BPA A: 165. Environmental Compliance for Projects on Forest Service Lands 01/31/2020 12/31/2019
Finalize designs B: 175. Nevada Creek Barrier Replacement Design 01/31/2020 01/30/2020
Finalize Designs C: 175. White Creek Barrier Replacement Design 01/31/2020 01/30/2020
Finalize Designs D: 175. Mike White Creek Barrier Replacement Design 01/31/2020 01/30/2020
Road Decommissioning Complete E: 33. Lolo 1st 50 Road Decommissioning 10/31/2019 10/31/2019
Finalize Designs F: 175. Musselshell Meadows Berm Removal/Floodplain Re-connection Design 01/31/2020 01/30/2020
Construct Beaver Dam Analogs on Musselshell Creek G: 29. Construct Beaver Dam Analogs on Musselshell Creek 08/30/2019 08/30/2019
Fence Maintained H: 186. Maintain Fence 06/10/2019 06/10/2019
Complete Topographic Surveys I: 115. Collect Topographic Information for Future Water Diversion Designs 09/30/2019 09/30/2019
Road Decommissioning and Culvert Surveys J: 115. Road Decommissioning and Culvert Surveys 11/30/2019 09/30/2019
Riparian Planting K: 47. Riparian Planting 11/30/2019 10/31/2019
Treat Exotic Invasive Species L: 199. Treat Exotic Invasive Species 09/30/2019 09/30/2019
Manage Projects and Administrative duties M: 119. Manage Projects and Administrative duties 01/31/2020 01/30/2020
Attach 2019 Annual Report O: 132. Annual Report February 2019 - January 2020 01/31/2020 01/30/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 4 instances of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 4 instances of WE 175 Produce Design
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 4 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance for Projects on Forest Service Lands 02/01/2019
B 175 Nevada Creek Barrier Replacement Design 04/18/2019
C 175 White Creek Barrier Replacement Design 04/18/2019
D 175 Mike White Creek Barrier Replacement Design 04/18/2019
E 33 Lolo 1st 50 Road Decommissioning 07/08/2019
F 175 Musselshell Meadows Berm Removal/Floodplain Re-connection Design 04/18/2019
G 29 Construct Beaver Dam Analogs on Musselshell Creek 12/19/2018
H 186 Maintain Fence 12/19/2018
I 115 Collect Topographic Information for Future Water Diversion Designs 12/19/2018
J 115 Road Decommissioning and Culvert Surveys 12/19/2018
K 47 Riparian Planting 12/19/2018
L 199 Treat Exotic Invasive Species 12/19/2018
M 119 Manage Projects and Administrative duties 02/01/2019
N 185 Periodic Status Reports for BPA 02/01/2019
O 132 Annual Report February 2019 - January 2020 02/01/2019